Project Overview

The ABC Jubail DC – Cheetah Project, developed for Al Jomaih Beverages Co. Ltd. in the Royal Commission Industrial City, Jubail, Saudi Arabia, is being executed as a turnkey project, including comprehensive infrastructure, construction, architectural, electrical, and mechanical works.

Client

Al Jomaih Beverages Co. Ltd.

Project Area

9.200 m2

Start Date

Oct 1, 2024

Finish Date

May 31, 2025

ABC Jubail DC – Cheetah Project

The ABC Jubail DC – Cheetah Project, developed for Al Jomaih Beverages Co. Ltd. in the Royal Commission Industrial City, Jubail, Saudi Arabia, is being executed as a turnkey project, including comprehensive infrastructure, construction, architectural, electrical, and mechanical works.

Client: Al Jomaih Beverages Co. Ltd.
Project Description: ABC Jubail DC – Cheetah Project
Location: Royal Commission Industrial City, Jubail, KSA
Scope of Work: Turnkey; Infrastructure, Construction, Architectural Works, Electrical and Mechanical Works
Structural System: Steel Structure
Total Covered Area: 9,200 m²
Start Date: October 2024
Completion Date: April 2025
Design: Gulf Consultant

ABC Jubail DC – Cheetah Project | Turnkey Project

The ABC Jubail DC – Cheetah Project, developed for Al Jomaih Beverages Co. Ltd. in the Royal Commission Industrial City, Jubail, Saudi Arabia, is being executed as a turnkey project, including comprehensive infrastructure, construction, architectural, electrical, and mechanical works.

The project, with a total enclosed area of 9,200 m², includes fully implemented production, storage, and administrative areas as well as complete technical infrastructure. The facility utilizes a steel structural system to ensure a durable and functional building.

The project is scheduled to be completed between October 2024 – April 2025 in accordance with the planned schedule and quality standards. The design has been prepared by Gulf Consultant.