Project Overview

For ABB Elektrik, the 10,817 m² distribution transformer facility and administrative building project constructed in Yukarı Dudullu Organized Industrial Zone, Istanbul was successfully completed on a turnkey basis.

Client

ABB Elektrik Sanayi A.Ş.

Project Area

10.817 m2

Start Date

Oct 1, 2005

Finish Date

Jul 30, 2006

ABB Electrical Distribution Transformers Facility

For ABB Elektrik Sanayi A.Ş., the Distribution Transformers Facility and Administrative Building project constructed in Yukarı Dudullu Organized Industrial Zone, Istanbul was completed by our company on a turnkey basis.

Employer: ABB Elektrik Sanayi A.Ş.
Project Description: Distribution Transformers Facility and Administrative Building
Location: Yukarı Dudullu Organized Industrial Zone, Istanbul
Scope of Work: Turnkey; Infrastructure, Construction, Architectural, Electrical and Mechanical Installation Works
Structural System: Prefabricated Structure
Total Enclosed Area: 10,817 m²
Start Date: October 2005
Completion Date: July 2006
Design: Ateş Architecture

ABB Electrical Distribution Transformers Facility and Administrative Building Project

For ABB Elektrik Sanayi A.Ş., the Distribution Transformers Facility and Administrative Building project constructed in Yukarı Dudullu Organized Industrial Zone, Istanbul was completed by our company on a turnkey basis.

In the project with a total enclosed area of 10,817 m², infrastructure, construction, and architectural works, as well as electrical and mechanical installation works were carried out. An efficient and durable facility suitable for industrial production needs was constructed using a prefabricated structural system.

The project was delivered between October 2005 – July 2006 in accordance with the planned schedule and quality standards. The design was carried out by Ateş Architecture.