Project Overview
For ABB Elektrik, the 10,817 m² distribution transformer facility and administrative building project constructed in Yukarı Dudullu Organized Industrial Zone, Istanbul was successfully completed on a turnkey basis.
Category
Client
ABB Elektrik Sanayi A.Ş.
Project Area
10.817 m2
Start Date
Oct 1, 2005
Finish Date
Jul 30, 2006




ABB Electrical Distribution Transformers Facility
For ABB Elektrik Sanayi A.Ş., the Distribution Transformers Facility and Administrative Building project constructed in Yukarı Dudullu Organized Industrial Zone, Istanbul was completed by our company on a turnkey basis.
Employer: ABB Elektrik Sanayi A.Ş.
Project Description: Distribution Transformers Facility and Administrative Building
Location: Yukarı Dudullu Organized Industrial Zone, Istanbul
Scope of Work: Turnkey; Infrastructure, Construction, Architectural, Electrical and Mechanical Installation Works
Structural System: Prefabricated Structure
Total Enclosed Area: 10,817 m²
Start Date: October 2005
Completion Date: July 2006
Design: Ateş Architecture
ABB Electrical Distribution Transformers Facility and Administrative Building Project
For ABB Elektrik Sanayi A.Ş., the Distribution Transformers Facility and Administrative Building project constructed in Yukarı Dudullu Organized Industrial Zone, Istanbul was completed by our company on a turnkey basis.
In the project with a total enclosed area of 10,817 m², infrastructure, construction, and architectural works, as well as electrical and mechanical installation works were carried out. An efficient and durable facility suitable for industrial production needs was constructed using a prefabricated structural system.
The project was delivered between October 2005 – July 2006 in accordance with the planned schedule and quality standards. The design was carried out by Ateş Architecture.