Project Overview

For Bosch Sanayi ve Ticaret A.Ş., the RBTR BU2 Block 310 Production and Office Buildings Project implemented in Nilüfer Organized Industrial Zone, Bursa was successfully completed by our company on a turnkey basis.

Client

Bosch Sanayi ve Ticaret A.Ş.

Project Area

22.151 m2

Start Date

Feb 1, 2012

Finish Date

Jan 18, 2013

RBTR BU2 Block – Production and Office Buildings

For Bosch Sanayi ve Ticaret A.Ş., the RBTR BU2 Block 310 Production and Office Buildings Project implemented in Nilüfer Organized Industrial Zone, Bursa was successfully completed by our company on a turnkey basis.

Employer: Bosch Sanayi ve Ticaret A.Ş.
Project Description: RBTR BU2 Block 310 Production and Office Buildings
Location: Nilüfer Organized Industrial Zone, Bursa
Scope of Work: Turnkey: Infrastructure Works, Construction Works, Architectural Works.
Structural System: Reinforced Concrete, Prefabricated Columns, Steel Roof Structure
Total Enclosed Area: 22,151 m²
Start Date: February 2012
Completion Date: January 2013
Design: Ateş Architecture, Engineering

Bosch RBTR BU2 Block 310 Production and Office Buildings | Turnkey Project

For Bosch Sanayi ve Ticaret A.Ş., the RBTR BU2 Block 310 Production and Office Buildings Project implemented in Nilüfer Organized Industrial Zone, Bursa was successfully completed by our company on a turnkey basis.

In the project with a total enclosed area of 22,151 m², a combination of structural systems was used, including a reinforced concrete structure, prefabricated columns, and a steel roof structure system. The building was designed in accordance with high durability, flexibility, and long-lasting usage criteria suitable for industrial production processes.

Within the scope of the project, infrastructure works, construction works, and architectural applications were carried out in an integrated manner; the works were completed within the planned schedule between February 2012 – January 2013. The architectural and engineering design of the project was carried out by Ateş Architecture & Engineering.

  • Distribution Transformer Facility and Administration Building

  • Infrastructure Expansion Project