Project Overview

For MODKAR Ambalaj Sanayi ve Ticaret A.Ş., the Carton Production Facility project implemented in Tekirdağ / Çorlu was planned in accordance with industrial production requirements and successfully completed.

Client

MODKAR Ambalaj Sanayi ve Ticaret A.Ş.

Project Area

21.750 m2

Start Date

Feb 1, 2005

Finish Date

Aug 30, 2005

MODKAR Packaging Carton Production Facility

For MODKAR Ambalaj Sanayi ve Ticaret A.Ş., the Carton Production Facility project implemented in Tekirdağ / Çorlu was planned in accordance with industrial production requirements and successfully completed.

Employer: MODKAR Ambalaj Sanayi ve Ticaret A.Ş.
Project Description: Carton Production Facility
Location: Çorlu, Tekirdağ
Scope of Work: Infrastructure, Construction, Architectural Finishing Works, Roof and Façade Cladding
Structural System: Prefabricated Reinforced Concrete
Total Enclosed Area: 21,750 m²
Start Date: February 2005
Completion Date: August 2005
Design:

MODKAR Packaging Carton Production Facility Project

For MODKAR Ambalaj Sanayi ve Ticaret A.Ş., the Carton Production Facility project implemented in Tekirdağ / Çorlu was planned in accordance with industrial production requirements and successfully completed.

Within the scope of the project with a total enclosed area of 21,750 m², infrastructure works, construction works, architectural finishing works, and roof and façade cladding applications were carried out. The structure was built using a prefabricated reinforced concrete structural system.

The project was completed between 1 February 2005 – 30 August 2005 in accordance with the specified schedule and quality standards.

  • Clariant Masterbatch Production Facility

  • Cooling Gas Filling Plant